Road closures will be taking place on three roads in Charminster over the next few months.
Almost five months of multi-phased roadworks will be taking place on Vicarage Lane, Mill Lane and Wanchard Lane.
These began on Saturday, January 27 and are expected to be completed by Saturday, June 15.
These closures will enable Scottish and Southern Power Distribution safe access to install 33kV cable to replace faulty cable.
- Vicarage Lane between January 27 and February 18, there will be three phases during this period.
- Mill Lane between February 14 and March 23, there will be two phases during this period.
- Wanchard Lane between April 18 and May 26, there will be three phases during this period.
- Wanchard Lane between May 26 and June 13.
- Vicarage Lane between June 1 and June 15.
An alternative route will be signed for each phase.
For further information about the work being undertaken and access arrangements, call Scottish and Southern Power Distribution on 07534591558.
To discuss the closure order, contact Dorset Council on 01305 221020.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel